Commencement of Work - Start the Job All home improvement contracts must include: the approximate dates on which construction is to begin; the approximate dates on which all construction is to be completed (not number of working days); what constitutes substantial commencement of the work; and a notice that failure of the contractor without lawful excuse to substantially commence work within 20 days from the approximate date specified in the contract when work will begin is a violation of Business and Professions Code section 7159
The dates need to be approximate only, since external factors such as the weather, or the availability of supplies might cause delays.
|
|